Poll: Will Phase One of the Second Avenue Subway Open on Time?

June 22, 2016

New Yorkers have learned to take deadlines and budgets from the MTA with a grain of salt, and the Second Avenue Subway may be the worst offender since it was first proposed all the way back in the 1920s. But the past couple years have restored some hope; in April 2015, it was announced that Phase I of the project was 82 percent complete and on track for its December 2016 opening, and last summer the MTA even went so far as to say the entire line could open sooner than originally planned.

But yesterday the Post reported that there’s a good chance the Second Avenue Subway won’t be finished on time, blaming construction crews not showing up for work. This has put inspections behind schedule, and therefore “the agency has only completed 67 percent of the testing and needs to do another 1,100 checks by October.”

RELATED:

Explore NYC Virtually

Leave a reply

Your email address will not be published.

Your email address will not be published. Required fields are marked *